Wuskwatim Generating Station

Construction of the 200-MW Wuskwatim generating station is under wayThe Wuskwatim generating station is under construction with an in-service-date of Q4 2011. The development will be comprised of a 200-MW, three-unit hydroelectric generating station located on the Burntwood River at Taskinigup Falls.

It will have a rated head of 21 m and be comprised of a close-coupled intake powerhouse, a three-bay spillway and earth dams. The development will involve the flooding of less than 1/2 km2 of land to create the forebay.

Scope of Services
KGS Acres, a Hatch affiliated company, is providing engineering services for the design and construction of the 200-MW Wuskwatim hydroelectric development.

KGS Acres’s scope of work includes:

  • Preparation of designs, tender drawings and specifications for
    • Construction camp and site infrastructure
    • Civil works
    • Gates and hoists
    • Electrical and mechanical equipment
  • Material listings for purchase of materials by the owner
  • Review of fabricator’s drawings
  • Assistance in scheduling and cost control
  • Assistance during commissioning
  • Preparation of operation and maintenance manuals
  • Liaison during construction with review of site designs and advice on ongoing details
  • Provision of construction management team staff

Detailed Characteristics

  • Powerhouse containing three vertical shaft, fixed blade and propeller turbines rated at 70 MW under a net head of 21 m
  • Turbine runners approximately 7 m in diameter
  • Umbrella-type generators, each rated at 87.4 MVA at 0.85 power factor
  • Powerhouse crane with a capacity of 240 Mg
  • Nine fixed-roller vertical lift gates in three intake structures. Each gate is to be approximately 5 m wide by 12.8 m high and will be equipped with a wire rope hoist
  • Three-bay spillway with vertical lift gates, each 9 m wide by 13 m high, with a total design discharge of 2650 m3/s
  • Approximately 120 000 m3 of concrete in the spillway, intake, powerhouse and auxiliary structures
    • Excavation of 800 000 m3 of rock and 800 000 m3 of overburden
  • Upstream channel improvements will be incorporated at the river’s outlet from Wuskwatim Lake
  • Approximately 460,000 m3 of earth and rockfill for dams to contain the resevoir and control water during construction
  • Construction camp to accommodate a workforce of approximately 800
  • Construction of a 50-km long road for access to the site

Awards

  • Award of Excellence and Keystone Award from Consulting Engineers of Manitoba, 2007
Project Stats
Client:
Manitoba Hydro

Location:
Burntwood River, Manitoba, Canada

Start:
August 2002

Completion:
Ongoing

Cost:
CDN$1.3 billion

See more Large Hydro projects >

Your Career Starts Here

Articles

See technical articles for the Energy sector.


Contacts

Alan O'Brien
Global Director
Renewable Power
North America
Tel: +1 905 357 6993

Web.LrgHydroelectricProjects@hatch.ca
Our Band of Principles